Itaipu used 12.7 million m³ of concrete in construction

Marco Três newsroom · edited by Annie GrellmannPortuguêsEspañol

Project gathered up to 40,000 workers on site

The construction of the Itaipu Hydroelectric Plant consumed 12.7 million cubic meters of concrete. At the peak of activities, the construction site employed 40,000 workers.

Itaipu used 12.7 million m³ of concrete in construction
Foto: Cmasi / Wikimedia · CC BY-SA 4.0

The Itaipu dam, located on the border between Foz do Iguaçu (Brazil) and Ciudad del Este (Paraguay), required an extraordinary volume of material during its construction. The concrete used in the project totaled 12.7 million cubic meters.

At the height of the project, the workforce on the site reached 40,000 people, reflecting the monumental scale of the binational undertaking.

Source: Midiamax

https://midiamax.com.br/trends/2026/09/27/construcao-itaipu-concreto-maracana

Share

Still have questions? Ask the border

Marco Três's AI answers instantly, only from verified guides and live data, never made up.

Ask my own question →

Read also

Live tools

Saiba de tudo antes de todo mundo

Câmbio, clima e o que importa nos três países, no seu e-mail, todo dia. Gratuito, sem spam.

✓ Marco Três fact-check

Content verified by the newsroom based on an official source: GNews Foz geral. Last checked: 9/27/2026. Found something inaccurate? We fix it fast. How we work.

Spotted something wrong? Tell us.

AI-automated curation with editorial supervision, your correction or suggestion helps keep things right.